# Isis Remediation v2 Milestones

Date: 2026-02-23  
Source: `ISIS_TODOS_2.md`,
`docs/domains/isis/remediation-v2/ISIS_REMEDIATION_V2_TICKETS.json`

## Goal

Define hard milestone dates for v2 delivery phases: Foundation, Expansion,
Certification, and Launch.

## Milestone Plan

| Milestone          | Date Range               | Scope                                                                                 |
| ------------------ | ------------------------ | ------------------------------------------------------------------------------------- |
| `M0 Foundation`    | 2026-02-23 to 2026-04-03 | Governance and foundational contract work (`WS00` to `WS03` + DoD alignment).         |
| `M1 Expansion`     | 2026-04-06 to 2026-05-29 | Runtime/serverless/platform capability expansion (`WS04` to `WS10`).                  |
| `M2 Certification` | 2026-06-01 to 2026-07-24 | UX, reliability, security, and operational closure (`WS11` to `WS18`).                |
| `M3 Launch`        | 2026-07-27 to 2026-10-30 | Matrix-scale certification and launch-readiness closure (`MXA`, `MXB`, `MXC`, `MXD`). |

## Gate Criteria

### Gate M0 -> M1 (target: 2026-04-03)

- All `WS00-*`, `WS01-*`, `WS02-*`, and `WS03-*` tasks are complete.
- V2 remediation artifacts regenerate cleanly with 1:1 ticket linkage.
- Severity rubric and sign-off matrix are active and referenced in governance.

### Gate M1 -> M2 (target: 2026-05-29)

- All `WS04-*` through `WS10-*` tasks are complete.
- Runtime, RunPod, and external integration capabilities meet defined acceptance
  criteria.
- No unresolved `critical` severity item remains in M1 scope.

### Gate M2 -> M3 (target: 2026-07-24)

- All `WS11-*` through `WS18-*` tasks are complete.
- Cross-functional sign-offs are complete for Certification gate.
- Quality, reliability, security, and operational checks pass.

### Final Launch Close (target: 2026-10-30)

- Matrix scope (`MXA-*`, `MXB-*`, `MXC-*`, `MXD-*`) is fully completed and
  certified.
- Launch gate sign-offs complete across Product, Platform, Creative Tech,
  Frontend, SRE, and Security.
- Final executive closure report published.

## Tracking Rules

- Milestone dates are fixed unless changed through program governance approval.
- Ticket milestone fields are generated from
  `scripts/isis/generate-remediation-backlog-v2.mjs` and must not be edited
  manually in generated files.
- Any milestone change requires regenerating v2 ticket artifacts.

## Traceability

Primary checklist item:

- `WS00-004`

Related tasks:

- `WS00-003`
- `WS00-005`
- `WS00-006`