# Isis Remediation Milestones (Phased Schedule)

Date: 2026-02-21  
Source: `ISIS_TODOS.md`, `docs/domains/isis/remediation/ISIS_REMEDIATION_TICKETS.json`

## Goal
Define explicit target dates for Phase 0/1/2/3 and establish gate-based progression criteria.

## Milestone Plan

| Milestone | Phase | Start Date | End Date | Focus |
|---|---|---|---|---|
| M0 Foundation | Phase 0 | 2026-02-23 | 2026-03-20 | Program setup and P0 execution blockers (`WS00`, `F01`, `F02`, `F03`, `F04`, `F15`) |
| M1 RunPod Productionization | Phase 1 | 2026-03-23 | 2026-04-17 | Provider/runtime productionization (`F05`, `F06`, `F07`, `F08`) |
| M2 Hardening and Parity | Phase 2 | 2026-04-20 | 2026-05-22 | Persistence, security, contract and test hardening (`F09`–`F14`, `F16`, `F17`, `F18`, parity items) |
| M3 Certification and Operational Closure | Phase 3 | 2026-05-25 | 2026-06-26 | Full certification, journey coverage, cutover and ops completion (`F19`, `F20`, `F21`, `F22`, gates) |

## Phase Gates

### Gate M0 -> M1 (2026-03-20)
- All `WS00` tickets complete.
- All `F01`/`F02`/`F03` tickets complete.
- Generation pipeline transitions jobs from submit to real execution.
- Canonical workflow schema agreed and enforced.

### Gate M1 -> M2 (2026-04-17)
- All `F05`/`F06`/`F07`/`F08` tickets complete.
- RunPod adapter no longer relies on placeholder cost/history functionality.
- Infrastructure drift detection and reconcile workflow operational.

### Gate M2 -> M3 (2026-05-22)
- All `F09`–`F14`, `F16`, `F17`, `F18` tickets complete.
- API/SDK parity checks pass in CI.
- Security and readiness checks are production-truthful and verified.

### Final Close (2026-06-26)
- All `WF-*`, `UX-*`, `OPS-*`, `GATE-*` tickets complete.
- 45/45 workflow certifications complete.
- Web app parity complete across all required interactions.
- Production cutover sign-off complete.

## Tracking Rules
- Every ticket in `ISIS_REMEDIATION_TICKETS.json` must have a milestone value.
- Any date changes require updating this file and regenerating ticket artifacts.
- No phase may start execution before the previous phase gate criteria are satisfied.