Status: Active
Owner: OSHUN Studio Architecture + OSHUN Data Platform + OSHUN Web + OSHUN BFF +
Platform SRE + Security and Compliance
Last Updated: 2026-02-23
Related:
docs/adr/ADR-0051-oshun-studio-backup-and-disaster-recovery-ux.mddocs/releases/v1/specs/studio-backup-and-disaster-recovery-ux-dependency-and-data-contract-map.md
Purpose#
Define primary journeys and deterministic edge-case behavior for Studio backup and disaster-recovery workflows.
This document is the execution artifact for OST-00307.
Personas#
- Disaster Recovery Operator
- Platform SRE Incident Commander
- Compliance Auditor
- Security Reviewer
- Domain Integration Engineer
Journey Principles#
- Recovery actions must be simulation-first and fail safely.
- Production failover/restore must be policy-gated and auditable.
- Cross-domain integrity checks must determine closure validity.
- Backup and recovery evidence must remain continuously observable.
1. Primary Journeys#
J1. Define Backup Plan Baseline#
Goal: Publish backup plan definitions for domains/services with explicit scope, cadence, and retention behavior.
Entry: Backup/DR workspace
Steps:
- Select source domain and backup scope.
- Define schedule, retention window, encryption profile, and owner metadata.
- Validate policy/schema compatibility.
- Publish backup plan version.
- Emit backup-plan governance audit event.
Success State:
- Backup plan baseline is valid, versioned, and available to operators.
J2. Run Restore Simulation and Impact Analysis#
Goal: Verify restore viability with dry-run simulation before execution.
Entry: Approved restore request
Steps:
- Select restore point and target scope.
- Validate restore-point integrity and snapshot coverage.
- Execute dry-run simulation and collect impact summary.
- Review duration, risk score, and affected service projections.
- Emit simulation result telemetry and audit evidence.
Success State:
- Restore simulation passes and produces deterministic execution prerequisites.
J3. Execute Policy-Gated Failover/Restore#
Goal: Perform controlled failover/restore action with explicit guardrails.
Entry: Simulation passed
Steps:
- Validate role, permission tier, and production approval requirements.
- Create execution checkpoint and rollback metadata.
- Execute restore/failover action against selected scope.
- Monitor execution status and error boundaries.
- Emit execution outcome and checkpoint evidence.
Success State:
- Failover/restore action completes with policy-compliant evidence.
J4. Verify Post-Recovery Integrity and Unblock Operations#
Goal: Confirm recovered state integrity across affected domains.
Entry: Execution success
Steps:
- Run domain-specific integrity and dependency checks.
- Compare restored state against expected recovery baseline.
- Identify unresolved discrepancies and severity.
- Record verification report and decision.
- Unblock operations only when verification is complete.
Success State:
- Recovery verification confirms safe state restoration.
J5. Recover DR Incident and Close#
Goal: Resolve failed or partial disaster-recovery attempts and close with evidence.
Entry: Open DR incident
Steps:
- Correlate plan, simulation, execution, and verification failures.
- Apply mitigation (rollback, checkpoint replay, scope reduction, patch).
- Re-run simulation/execution/verification sequence.
- Confirm telemetry and audit continuity restoration.
- Close incident with complete post-recovery evidence package.
Success State:
- DR workflow integrity is restored and closure is auditable.
2. Critical Edge Cases#
E1. Backup Plan Missing Schedule#
- Trigger: plan publish request omits schedule metadata.
- Required behavior: reject publish with
plan_schedule_required.
E2. Unsupported Backup Scope#
- Trigger: scope value is not recognized by policy registry.
- Required behavior: deny publish and return scope-validation error.
E3. Restore Point Integrity Failed#
- Trigger: selected restore point integrity state is failed.
- Required behavior: block simulation and execution.
E4. Restore Simulation Timeout#
- Trigger: dry-run simulation exceeds configured timeout.
- Required behavior: mark simulation failed and require operator retry/escalation.
E5. Production Execute Without CAB Approval#
- Trigger: production restore/failover requested without CAB evidence.
- Required behavior: hard deny and emit policy-denial audit event.
E6. Permission Tier Below Execute Requirement#
- Trigger: operator tier is below required execute tier.
- Required behavior: deny execution and preserve current state.
E7. Missing Execution Checkpoint#
- Trigger: execution starts without checkpoint/rollback metadata.
- Required behavior: fail closed and prevent action from running.
E8. Cross-Domain Dependency Verification Mismatch#
- Trigger: recovered domain state violates dependency constraints.
- Required behavior: keep incident open and block operation unblock.
E9. Verification Closure Attempt with Unresolved Issues#
- Trigger: closure requested while unresolved issue count > 0.
- Required behavior: deny closure and require remediation.
E10. Telemetry/Audit Sink Degradation#
- Trigger: recovery actions complete but telemetry/audit cannot persist.
- Required behavior: enter degraded-observability mode and block production promotions.
3. Journey-to-Surface Mapping#
| Journey | Primary Surface | Supporting Surfaces |
|---|---|---|
| J1 Define Backup Plan Baseline | Backup plan definition panel | Policy registry + schedule validators |
| J2 Run Restore Simulation | Restore simulation panel | Snapshot inventory + simulation orchestrator |
| J3 Execute Failover/Restore | Recovery execution panel | RBAC/tier engine + checkpoint services |
| J4 Verify Post-Recovery Integrity | Verification panel | Domain integrity checks + dependency graph services |
| J5 Recover DR Incident | Recovery incident panel | Observability dashboards + runbook orchestration |
4. Instrumentation Requirements#
Required events:
backup_dr_ux.journey.startedbackup_dr_ux.journey.step.completedbackup_dr_ux.journey.blockedbackup_dr_ux.journey.execution.failedbackup_dr_ux.journey.recoveredbackup_dr_ux.journey.completed
Required dimensions:
planId,planVersion,scope,sourceDomain,retentionDaysrestorePointId,simulationId,executionId,checkpointIdaction,releaseChannel,approvalTicket,permissionTierverificationId,unresolvedIssueCount,riskScoreactorId,actorRole,journeyId,stepId,outcome,reasonCode,latencyMs,traceId
5. Acceptance Criteria (OST-00307)#
OST-00307 is complete only when:
- At least five backup/disaster-recovery journeys are documented.
- At least ten deterministic edge cases are documented.
- Journey-to-surface mapping is explicit.
- Instrumentation requirements and dimensions are documented.