Date: 2026-02-21
Source: ISIS_TODOS.md, docs/domains/isis/remediation/ISIS_REMEDIATION_TICKETS.json
Goal#
Define explicit target dates for Phase 0/1/2/3 and establish gate-based progression criteria.
Milestone Plan#
| Milestone | Phase | Start Date | End Date | Focus |
|---|---|---|---|---|
| M0 Foundation | Phase 0 | 2026-02-23 | 2026-03-20 | Program setup and P0 execution blockers (WS00, F01, F02, F03, F04, F15) |
| M1 RunPod Productionization | Phase 1 | 2026-03-23 | 2026-04-17 | Provider/runtime productionization (F05, F06, F07, F08) |
| M2 Hardening and Parity | Phase 2 | 2026-04-20 | 2026-05-22 | Persistence, security, contract and test hardening (F09–F14, F16, F17, F18, parity items) |
| M3 Certification and Operational Closure | Phase 3 | 2026-05-25 | 2026-06-26 | Full certification, journey coverage, cutover and ops completion (F19, F20, F21, F22, gates) |
Phase Gates#
Gate M0 -> M1 (2026-03-20)#
- All
WS00tickets complete. - All
F01/F02/F03tickets complete. - Generation pipeline transitions jobs from submit to real execution.
- Canonical workflow schema agreed and enforced.
Gate M1 -> M2 (2026-04-17)#
- All
F05/F06/F07/F08tickets complete. - RunPod adapter no longer relies on placeholder cost/history functionality.
- Infrastructure drift detection and reconcile workflow operational.
Gate M2 -> M3 (2026-05-22)#
- All
F09–F14,F16,F17,F18tickets complete. - API/SDK parity checks pass in CI.
- Security and readiness checks are production-truthful and verified.
Final Close (2026-06-26)#
- All
WF-*,UX-*,OPS-*,GATE-*tickets complete. - 45/45 workflow certifications complete.
- Web app parity complete across all required interactions.
- Production cutover sign-off complete.
Tracking Rules#
- Every ticket in
ISIS_REMEDIATION_TICKETS.jsonmust have a milestone value. - Any date changes require updating this file and regenerating ticket artifacts.
- No phase may start execution before the previous phase gate criteria are satisfied.